| |
* Renovation of rip rap
* Strengthening of dam
* Establishment of bathing steps
* Removal of unnecessary trees from dam
* Placing of Gabion wall
* Establishment of tor filter & tor drain
* Establishment of drainage system on dam
* Construction of access road for inspection
* Repairing of sluices
* Repairing of office building for maintenance
* Repairing of gate |
| |
|
| |
|
| |
Renovation of Kanthale Reservoir
is Progressing Under DSWRPP |
| |
Steps passing over rehabilitation process |
| |
Environmental Assessment and EMP were cleared by both World Bank and CEA
---------------------------------------------------------------- |
| |
Awareness programmes were conducted at district level to aware stakeholders on rehabilitation programme
---------------------------------------------------------------- |
| |
Dam Construction Monitoring Committee was established to monitor entire rehabilitation process
---------------------------------------------------------------- |
| |
Detail design for civil works was developed by ID and reviewed by DSRP for implementation
---------------------------------------------------------------- |
| |
Final conceptual designs for the dam was submitted by Implementation Support Consultant on 23rd March 2010
---------------------------------------------------------------- |
| |
Maximising the opportunity of the prevailed drought during latter part of 2009, installation of emergency gates to RB Sluice of the dam was completed. This was undertaken by Government Factory.
---------------------------------------------------------------- |
| |
Inspection boat, Pickup, Digital camera, Bush cutter, Tirfort wincher, Chain saw, Desktop computer and software, printer, Multimedia Projector, generator, backhoe loader, inspection boat and safety jackets and mobile pickup were provided to dam office to improve the O&M and capacity to ensure safety of the Dam.
---------------------------------------------------------------- |
| |
Remedial work contract worth of Rs 118.85 million was awarded to M/S Orient Construction Co. (Pvt) Ltd. on 17th Sept 2010 and contractor mobilized work 1st Oct, 2010.
----------------------------------------------------------------- |
| |
Dam construction Monitoring (Oversight) Committee was established and held a several meetings to monitor entire rehabilitation process
---------------------------------------------------------------- |
| |
EMP has been implemented by contractor and monitoring by PMU
---------------------------------------------------------------- |
| |
Contractor completed 10% physical progress and 2.19% financial progress as of 30th April 2011
----------------------------------------------------------------- |
| |
Contractor has completed 100% security and insurance, 100% clearing work, 50% contractor facility, 57% toe drain and access road,
---------------------------------------------------------------- |
| |
|